Final Capping Works at Ffridd Rasus Landfill Site in Harlech, Wales

 

Client: Gwynedd Council

Contract Term: Feb 2014 – Apr 2014 

Contract Value: £0.48 million

Key Project Elements

  • Shaping of waste body to design profile.
  • Placing of 150mm of sub soil over shaped waste 
  • Deploy & weld lining layers, 2mm lldpe liner & surface water drainage geocomposite 20,000m2 
  • Placing of 750m of shale on-top of the HDPE Liner 
  • Installed drainage layers to the perimeter of the capped area 
  • Connected the gas wells to the existing flairs on-site

Back to Capping Works | Next