East Road Rehabilitation at Foynes Port in Co. Limerick
Client: Shannon Foynes Port Company
Contract Term: Jan 2014 – Mar 2014
Contract Value: €0.143 million
Key Project Elements
- Implemented & maintained a temporary diversion of traffic during works
- Carried out all site clearance & preparation work
- Installation of drainage 35m x 150mm & service ducts 34m x 300mm
- Construction of 116m of carriageway
- Construction of 126m of concrete kerb and 128m of drop kerb
- Installation of 4 x trapped gullies with a class D440 grating
- Installation of 1 x oil interceptor with D400 cover & frame
- Carried out subsequent earthworks & landscaping